Preparing the server for operation
Procedure
- Install any options or cables previously removed to access the TPM connector.
- If removed, install the air baffle.
- Install the access panel.
- Install the front bezel.
-
Do one of the following:
If the server is in tower mode: Position the tower server for operation.
If the server is in rack mode: Install the server on the tray.
- Connect all peripheral cables to the server.
-
Connect the power cords:
- Connect each power cord to the server.
- Connect each power cord to the power source.
- Power up the server.
The installation is complete.