Installing the energy pack option

Hewlett Packard Enterprise now offers two options as a centralized backup power source for backing up write cache content on Smart Array controllers if there is an unplanned server power loss. Only one energy pack is required per server, as it can support multiple devices.
Procedure
  1. Power down the compute module.
  2. Remove the compute module.
  3. Place the compute module on a flat, level work surface.
  4. Remove the access panel.
  5. Facing the front of the compute module, remove the DIMM baffle from the system board.
    Removing the DIMM baffle.
  6. Install the energy pack.
    Installing the energy pack into the DIMM baffle.
  7. Install the DIMM baffle.
  8. Connect the energy pack to the system board. To locate the energy pack option connector, see System board components.
    Plugging in the energy pack.
    NOTE: The port location for the energy pack has changed from previous releases. Plug the energy pack into the port located under the mezzanine option card.
  9. Install the mezzanine option card.
  10. Install the access panel.
  11. Install the compute module.
  12. Power up the compute module.